Archive for the ‘Construction’ category

Revisiting the Bioswales!

October 28th, 2010

In early October, students and young professionals from the Water Environment Federation (WEF) constructed a new bioswale for the Holy Cross Project to help manage storm water runoff while removing silt and pollution – since the site is prone to some flooding during heavy rainfall (i.e. “severe wet weather occurrences”). The group organized this special project, in coordination with Global Green and Groundwork New Orleans as part of a community service project to benefit the Lower Ninth Ward while in New Orleans for WEFTEC® 2010, the world’s largest annual water quality conference and exhibition.

PHOTO: Darryl Malek-Wiley

During the event, volunteers planted several wetland and wet-weather species, including spartina, horsetail, irises, cattails, red maple trees, cypress trees, and huckleberry.

Bioswale Construction: The site had been prepped and excavated prior to the volunteers’ arrival on Saturday. Archer Western Alberici along with Bottom Line Equipment, Storm Hunger Hauling and Delta Mining cleared and excavated the site and mixed the top soil used for the bioswale. When volunteers arrived, they first dug trenches and placed perforated pipe bundles designed to serve as underground water retention and collection. These areas were then backfilled with gravel and will operate as dry streams. The areas around the dry streams were filled with the top soil mix and then planted and mulched.

Thanks to all the volunteers who worked to construct this important addition as part of the “Bioswales in the Bayou” event. Nearly a month later, everything looks great!

July Update: New Construction

July 16th, 2010


405 Andry Street



401 Andry kitchen



401 Andry bedroom



401 Andry living room

The progress continues on Global Green’s single family homes at 401 and 405 Andry Street:

  • All flooring (FSC certified) and lights (energy efficient) are installed
  • Driveway to be poured today
  • Countertops to be installed today
  • Appliances to be installed next week

Stay tuned for more developments!


June Update: New Construction

June 11th, 2010



One important addition to the new houses at 401 and 405 Andry is the use of spray foam insulation to improve weatherization and dramatically reduce energy loss.

May Update: New Construction

May 5th, 2010


Progress continues on the new single-story homes at 401 and 405 Andry: finalizing the external envelope and more.

April Update: New Construction

April 14th, 2010



Progress on the two new single-story homes at 401 and 405 Andry Street continues, with foundations completed and framing using FSC certified wood (Forest Stewardship Council) underway.

Breaking Ground: Two New Houses Start Construction

March 21st, 2010


In mid-March, Global Green broke ground on houses #4 and #5 – as part of the planned five single-family homes – for the Holy Cross Project. These two new additions will be the first single-story houses (two bedrooms, one bath) on the site. Like their two-story neighbors, 401 and 405 Andry Street will utilize solar electric along with a wide range of interior and exterior green design features. We expect these two new houses to be complete by the end of 2010. Stay tuned!